One Mile Bridge Replacement

Demolition and disposal of existing a 106 year old bridge and replace it with a 246 foot U-80 bridge. Project was located in the Tacoma Watershed 300 feet upstream of the main intake of Tacoma’s water supply making safety of the drinking water of the utmo

Demolition and disposal of an existing 106-year-old steel truss span bridge and construction of a 246-foot U-80 bridge replacement was no small feat. Especially when the location was only 300 feet upstream from the main intake of Tacoma Washington’s water supply. This made drinking water a top concern as our team worked diligently to ensure public safety and finished the project within six weeks and ahead of schedule.

  • Lead paint containment through the demolition and disposal of existing bridge
  • Main Line Road to Howard Hansen Dam could only be closed for six weeks
  • Pivetta completed the project 12 days ahead of schedule